Construction progress of residential complex SENAT September 2022

Dear buyers of the residential complex "SENAT". We inform you that all construction and installation works are underway!

As of September 7, 2022, the following has been completed:

And the turn of construction:

Section #1:

Complete monolithic works have been completed.
Work on the arrangement of the roof is actively being carried out, 90% of the work is completed.
Installation of storm drains has been completed.
Masonry work on the external walls has been completed.
The execution of masonry works of inter-apartment and inter-room walls has been completed.
Work on the arrangement of window structures is being carried out. 20% is arranged.
Facade work has begun.
The elevator equipment is being actively installed. Freight elevators have been installed.
Smoke exhaust fans are installed.
The tower cranes were dismantled.

Section #2:
Complete monolithic works have been completed.
The installation of the roof is completed.
Installation of storm drains has been completed.
Masonry work on the external walls has been completed.
The execution of masonry inter-apartment and interior walls has been completed.
Work on the arrangement of window structures is being carried out. 100% arranged.
Facade work has begun.
The elevator equipment is being actively installed. Freight elevators have been installed.
Smoke exhaust fans are installed.
The tower cranes were dismantled. The elevators have been installed and are already working.

Facade works are actively underway.