Construction progress of the Family&Friends residential complex August 2022

Dear buyers of the "Family&Friends" residential complex. We inform you that all construction and installation works are underway!

As of September 7, 2022, the following was completed: Section B
Window structures are installed on the 20th floor.
Elevator installation works are underway.
Installation of electric risers is underway
Work is underway to insulate the facade.
Heating and water supply is distributed apartment by apartment at the level of the 20th floor.
Apartment-by-apartment distribution of electricity is being carried out at the level of the 20th floor.
Work is underway to install a sand-cement screed on the 18th floor.
Plastering of common areas on the 14th floor is underway.


Section Z
Work is underway to insulate the facade.
Construction of external and internal walls is being carried out on the 20th floor.

Section M
Arrangement of external and internal walls is carried out from the 20th to the 25th floor
Sewer risers are being installed
Heating and water supply distribution is carried out apartment by apartment at the level of the 15th floor.
Apartment-by-apartment distribution of electricity is being carried out at the level of the 15th floor.
Work is underway to install a sand-cement screed at the level of the 13th floor.