Construction progress of the ARIA residential complex August 2022

Dear buyers of the "ARIA" residential complex. We inform you that all construction and installation works are underway!

As of September 7, 2022, the following has been completed:
1. Insulation and reinforcement of the ceiling in the arch on the side of Druzhba Narodov boulevard between the 2nd and 3rd sections.
2. Installation of a suspended ceiling in the arch from the side of the street. Czech Within its section. Installation of a suspended ceiling in the arch on the side of Druzhba Narodiv boulevard between the 2nd and 3rd sections.
3. Installation of sewerage outside the building site (shaft).
4. Installation of the heating, water supply and sewage system, section #1, 1st floor. (Offices). Installation of the heating system, water supply and sewerage, section #2, 1st floor. (Offices). Installation of the heating system, water supply and sewerage, section #3, 1st floor. (Offices). Installation of the heating system, water supply and sewerage, section #4, 1st floor. (Offices).
5. Installation of screed sec #1 1 floor (offices). Installation screed sec #2 1 floor (offices). Installation screed sec #3 1 floor (offices).
6. Masonry of the walls of the first floor, section #4.
7. Painting ventilation ducts on the roof of the building, section #1,2,3,4,5. Plastering of the staircase, section #2, 21-26 floors. Plastering of the stairwell (firehouse) section No. 1 Job 3-15.

8. Excavation of a pit on the project mark on the side of Druzhba Narodov Boulevard within its and 2nd sections. Installation of a retaining wall on the side of Druzhba Narodov Boulevard within its and 2nd sections. Arrangement of plastering waterproofing of the retaining wall on the side of Druzhba Narodov boulevard within its and the 2nd section on both sides.

9. Facade section #1
Installation of double-glazed windows, installation of metal brackets, installation of an aluminum frame, installation of abutment, installation of aluminum brackets under the frames, installation of aluminum brackets of the NVF, installation of the insulation of the NVF, installation of the aluminum radiating NVF.

10. Facade section #2
Installation of double-glazed windows, installation of metal brackets, installation of an aluminum frame, installation of abutment, installation of aluminum brackets under the frames, installation of aluminum brackets of the NVF, installation of the insulation of the NVF, installation of the aluminum radiating NVF.

11. Facade section #3
Installation of double-glazed windows, installation of metal brackets, installation of an aluminum frame, installation of abutment, installation of aluminum brackets under the frames, installation of aluminum brackets of the NVF, installation of the insulation of the NVF, installation of the aluminum radiating NVF.
12. Facade section #4
Installation of double-glazed windows, installation of metal brackets, installation of an aluminum frame, installation of abutment, installation of aluminum brackets under the frames, installation of aluminum brackets of the NVF, installation of the insulation of the NVF, installation of the aluminum radiating NVF.

13. Facade section No. 5
Installation of double-glazed windows, installation of metal brackets, installation of an aluminum frame, installation of abutment, installation of aluminum brackets under the frames, installation of aluminum brackets of the NVF, installation of the insulation of the NVF, installation of the aluminum radiating NVF.

14. Arrangement of side stone (pavement, flower beds) in the yard of the house within section No. 3, 2, 1. Planning with crushed stone to the design mark in the yard of the building of the road and sidewalk within the boundaries of section #3,2,1. Arrangement of a fem in the yard of the building of the road and sidewalk within the boundaries of section #3,2,1.

15. Welding of trusses (metal frame) to cover the exit, entrance to the parking lot from the side of the street. Czech Within its section. Welding of trusses (metal frame) to cover the exit, entrance to the parking lot from the side of Druzhba Boulevard
Narodov between the 2nd ha Zyu section.

16. Installation of entrance doors to apartments, section #1, 3-10 floors.