Construction Progress at the Senat Residential Complex, August 2026
The Senat Residential Complex is in the final stages of construction. Here’s what’s
happening in September 2026:
🔹The rooftop gas boiler room has been fully installed; the equipment has been configured
and is ready for startup
🔹The building’s structural frame has been erected, and final facade cladding is underway
🔹Inside the apartments, the floors are ready for final finishing, radiators
are connected, and internal utility lines have been installed
🔹Work in common areas and on the open terraces has been completed
🔹The pump station and electrical panel room have been installed
🔹The entrance area is in the final stages of finishing
It’s time to choose your apartment in the Senat residential complex. Message us directly to find out
about available options.