Construction progress of the Senat residential complex September-October 2022

Back

Dear buyers of the residential complex "SENAT". We inform you that all construction and installation works are underway:

And the turn of construction:

Section #1:

Complete monolithic works have been completed.

Roof installation work is actively being carried out, 98% of the work is completed.

Installation of storm drains has been completed.

Masonry work on the external walls has been completed.

The execution of masonry works of inter-apartment and inter-room walls has been completed.

Work on the arrangement of window structures is being carried out. 50% arranged.

Facade work has begun.

The installation of the elevator equipment has been completed.

Smoke exhaust fans are installed.

The tower cranes were dismantled.

Section #2:

Complete monolithic works have been completed.

The installation of the roof is completed.

Installation of storm drains has been completed.

Masonry work on the external walls has been completed.

The execution of masonry inter-apartment and interior walls has been completed.

The installation of window structures has been completed. 100% arranged.

Facade works are actively being carried out.

The installation of the elevator equipment has been completed.

Smoke exhaust fans are installed.

The tower cranes were dismantled.

Other news

Company News

27 October, 2022

Construction progress of the ARIA housing complex September-October 2022

Company News

27 October, 2022

Construction progress of the Family&Friends residential complex September-October 2022