Construction Progress at Orange City Residential Complex, June 2026
Dear Orange City Residential Complex Buyers, We would like to inform you that
all construction and installation work is currently underway:
1) Masonry work:
- exterior walls are 97% complete,
- interior walls and partitions in Section #2 are complete up to and including the 26th floor,
- interior walls and partitions in Section #1 are approximately 80% complete.
2) Facade:
- One end wall has been completed,
- Brackets for air conditioning units are currently being installed,
- Insulation work is underway on the walls and balconies on both sides of the building.
3) Roof:
- Masonry work on the roof extensions is fully complete,
- Insulation and screed work on Section #2 are fully complete,
- Roof insulation on Section #1 is fully complete.
4) Ventilation:
- Installation of smoke exhaust fans has begun in Section #2.
5) Electrical:
- Cable trays along the risers have been fully installed,
- Installation of lighting cables is underway.
6) Windows:
- Fully installed in Section #2,
- 85% installed in Section #1.
7) Plumbing:
- Water, sewer, fire protection, and heating risers have been fully installed
in Section #2,
- Fan pipes are being installed in Section #2,
- Installation of cast-iron sewer pipes in the basement is in its final stages.