Construction Progress at the Family&Friends Residential Complex, September–October 2026

Back

Dear Family&Friends Residential Complex buyers. We would like to inform you that all construction and installation work is underway:

Section Z

Facade work is being carried out.

Plastering work has been completed in the common areas on the 19th floor.

Plastering of walls and tile installation on the floors of the entrance area and utility rooms on the first floor have been completed.

Tile installation is underway on the 20th floor.

Apartment doors have been installed up to the 14th floor.

Access hatches to utility lines are being installed on the floors.

Preparatory work for elevator installation is underway.

Section M

Facade work is underway.