Dear buyers of the Family&Friends Residential Complex. We would like to inform you that

all construction and installation work is currently underway:

Section Z

Facade work is being carried out.

Plastering work is being performed in the common areas on the 19th floor.

Plumbing work is underway to install water supply risers,

heating, and the fire protection system for the second zone.

Finishing work is underway in common areas,

utility rooms, and the first-floor entrance lobby.

Tile installation is underway on the 14th floor.

Apartment doors have been installed on floors 3 through 9.

Section M

Facade work is underway.